Construction of the Horizontal Infrastructure Project of the Clark International Airport New Terminal Building Project (Formerly Clark Airport Low Cost Terminal)
Scope of Works: Demolition of affected taxiways and old runway; Construction of new taxiways; Conversion of old runway to taxiway (G); Construction of taxiway shoulders; Construction of new apron, apron lighting, drainage and other embedded utilities prerequisite to concrete pavement; Installation / application of newly required markings and visual aids (signage and lightings) on taxiways and apron; Required grading of buffer and appurtenant areas for drainage and other related facilities; and Sodding of affected areas .
Location: Philippines, Central Luzon, Pampanga, Clark Freeport Zone
Project Cost: PHP 2,407,743,122.79
Date Completed: December 2018 to March 2021

Construction of Multi-Purpose Building, Las Piñas City
Scope of Works: Construction of Multi-Purpose Building, Las Piñas City
Location: Philippines, Muntinlupa City, Las Piñas
Project Cost: PHP 144,741,202.60
Date Completed: October 2020 to November 2021

Rehabilitaiton and Reconstruction of Roads with Slips, Slope Collapse, and Landslide along Tablas Circumferential Road, Romblon
Scope of Works: Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse and Landslide
Location: Philippines, MIMAROPA Region, Romblon
Project Cost: PHP 128,098,069.24
Date Completed: May 2021 to May 2022

Rehabilitation and Reconstruction of Roads with Slips, Slope Collapse, and Landslide along Tablas Circumferential Road, Romblon
Scope of Works: Roads: Construction – slope protection using structural measures (revetment, retaining structures, wirenet)
Location: Philippines, MIMAROPA Region, Romblon
Project Cost: PHP 137,313,210.97
Date Completed: April 2021 to April 2022

Rehabilitation and Reconstruction of Roads with Slips, Slope Collapse, and Landslide along Romblon-Cogon-Sablayan Road, Romblon
Scope of Works: Roads: Construction – slope protection using structural measures (revetment, retaining structures, wirenet)
Location: MIMAROPA Region, Romblon, Philippines
Project Cost: PHP 171,404,431.97
Date Completed: April 2021 to April 2022