Philippines

Construction of Tertiary Distribution System (Angat Water Optimization Project) at Tala Estate, North Caloocan
Scope of Works: Construction of tertiary distribution system at Tala Estate, Caloocan City.
Location: Philippines, NCR, Metro Manila, Caloocan City
Project Cost: PHP 138,533,616.00
Date Completed: July 2000 to April 2002

Planning, Design, Construction and Site Development of the Proposed Hawker’s Plaza
Scope of Works: Development of the Proposed Hawker’s Plaza Calapan City Public Market; Planning, Design, Construction & Site Development of the Proposed Hawker’s Plaza at the Calapan City Public Market.
Location: Philippines, MIMAROPA Region, Calapan
Project Cost: PHP 12,047,747.00
Date Completed: November 2012 to March 2013

Planning, Design, Construction & Site Development of Calapan City Public Market & Passenger Terminal
Scope of Works: Planning, design, construction and site development of Calapan Public Market and passenger terminal.
Location: Philippines, MIMAROPA Region, Calapan
Project Cost: PHP 212,518,031.71
Date Completed: June 2009 to March 2011

Supply, Installation & Commissioning of Elevator & Escalator, Calapan City Public Market & Passenger Terminal in San Vicente North, Calapan City
Scope of Works: Supply, Installation & Commissioning of Elevator & Escalator, Calapan City Public Market & Passenger Terminal in San Vicente North, Calapan City
Location: Philippines, MIMAROPA Region, Calapan
Project Cost: PHP 12,400,00.00
Date Completed: October 2010 to January 2011

Financing and Development of the 50 Has. Resettlement Project, Phase 1, Brgy. Poblacion, Muntinlupa City
Scope of Works: Site and land development of 50 hectares reserved area including survey works, drainage, water supply, sewer system, road works and power supply.
Location: Philippines, NCR, Muntinlupa City, Brgy. Poblacion
Project Cost: PHP 164,021,155.14
Date Completed: July 2007 to October 2009

Rehabilitation of Surigao – Davao Coastal Road Manay – Mati
Scope of Works: This project includes improvement and widening of the existing road of about 70.42 kms. closely following the existing alignment, Port Cement Concrete Pavement (PCCP) has 6.70 meter width, subbase shoulder and improvement of drainage structures, provision of road protection works and construction of bridge.
Location: Philippines, Mindanao, Davao, Davao Oriental
Project Cost: PHP 756,668,473.73
Date Completed: October 2004 – September 2008

Construction of Multi-Purpose Building, Las Piñas City
Scope of Works: Construction of Multi-Purpose Building, Las Piñas City
Location: Philippines, Muntinlupa City, Las Piñas
Project Cost: PHP 144,741,202.60
Date Completed: October 2020 to November 2021

Completion of Remaining Land Dev’t Works, Garbage Disposal, Construction of Sewage of Treatment Plant and Repair of Permanent Housing in Smokey Mountain
Scope of Works: Land development works, garbage disposal, construction of 2 unit Sewerage Treatment Plants, Repair of permanent housing in Smokey Mountain Development Reclamation Project
Location: Philippines, NCR, Metro Manila, Tondo
Project Cost: PHP 217,993,931.95
Date Completed: March 2004 to January 2006

Construction of the Horizontal Infrastructure Project of the Clark International Airport New Terminal Building Project (Formerly Clark Airport Low Cost Terminal)
Scope of Works: Demolition of affected taxiways and old runway; Construction of new taxiways; Conversion of old runway to taxiway (G); Construction of taxiway shoulders; Construction of new apron, apron lighting, drainage and other embedded utilities prerequisite to concrete pavement; Installation / application of newly required markings and visual aids (signage and lightings) on taxiways and apron; Required grading of buffer and appurtenant areas for drainage and other related facilities; and Sodding of affected areas .
Location: Philippines, Central Luzon, Pampanga, Clark Freeport Zone
Project Cost: PHP 2,407,743,122.79
Date Completed: December 2018 to March 2021

Reconstruction, Widening and Extension of R.C. Pier
Scope of Works: Demolition of existing R.C. deck, cutting of existing R.C. piles (105 units), reconstruction, widening and extension of R.C. Pier-Breakwater (15.0m x 105.0m) and mooring / fendering system (14/22 sets).
Location: Philippines, Visayas, Eastern Visayas, Southern Leyte
Project Cost: PHP 91,338,558.20
Date Completed: December 2004 to October 2006