Construction of Three (3) Buildings for Camarin Medium Rise Housing Project

Scope of Works: Design and construction of three (3) medium rise building including land development

Project Cost: PHP 38,319,286.71

Date Completed: April 2002 to September 2003

Smokey Mountain Development and Reclamation Project

Scope of Works: Reclamation of 79 hectares with containment structures for passenger cargo terminal, port and berthing facilities, dredging/removal of unsuitable materials. Land Filling with compaction. Dredging of South ends and North portion of the 79 hectares, construction of temporary housing and construction of 21- five-storey building permanent housing including site development works.

Project Cost: PHP 4,760,248,791.61

Date Completed: January 1996 to May 2002

Financing and Development of the 50 Has. Resettlement Project, Phase 1, Brgy. Poblacion, Muntinlupa City

Scope of Works: Site and land development of 50 hectares reserved area including survey works, drainage, water supply, sewer system, road works and power supply.

Project Cost: PHP 164,021,155.14

Date Completed: July 2007 to October 2009

Completion of Remaining Land Dev’t Works, Garbage Disposal, Construction of Sewage of Treatment Plant and Repair of Permanent Housing in Smokey Mountain

Scope of Works: Land development works, garbage disposal, construction of 2 unit Sewerage Treatment Plants, Repair of permanent housing in Smokey Mountain Development Reclamation Project

Project Cost: PHP 217,993,931.95