Clark International Airport Corporation (CIAC)
Construction of the Horizontal Infrastructure Project of the Clark International Airport New Terminal Building Project (Formerly Clark Airport Low Cost Terminal)
Scope of Works: Demolition of affected taxiways and old runway; Construction of new taxiways; Conversion of old runway to taxiway (G); Construction of taxiway shoulders; Construction of new apron, apron lighting, drainage and other embedded utilities prerequisite to concrete pavement; Installation / application of newly required markings and visual aids (signage and lightings) on taxiways and apron; Required grading of buffer and appurtenant areas for drainage and other related facilities; and Sodding of affected areas .
Location: Philippines, Central Luzon, Pampanga, Clark Freeport Zone
Project Cost: PHP 2,407,743,122.79
Date Completed: December 2018 to March 2021
Construction of Taxiway Access Road at Clark International Airport South-End Area
Scope of Works: Construction of New Taxiways and access road at Clark International Airport South End Area which includes construction of Taxiway shoulders, apron, drainage, markings and visual aids, and other related works.
Location: Central Luzon, Pampanga, Clark Freeport Zone
Project Cost: PHP 86,975,099.26
Date Completed: June 2019 to February 2021