Land Development of the MWSS Corporate Office Employees Housing Project
Scope of Works: Construction of roads, drainage, sewer system, water distribution, asphalt pavement, electrical works and water supply system.
Location: Philippines, NCR, Quezon City
Project Cost: PHP 22,710,232.83
Date Completed: December 2003 to November 2004

Package 6A: Secondary Road (Pasong Tamo) Metro Manila Urban Transport Integration Project, Phase 1
Scope of Works: Construction along Arnaiz Ave. to J.P. Rizal St. for the removal and replacement of the existing concrete pavement, drainage structure / reinforcement of box culvert, curbs and gutters, sidewalk, road signs and road markings, streetlights and landscaping works.
Location: Philippines, NCR, Makati City, Pasong Tamo
Project Cost: PHP 109,144,023.01
Date Completed: June 2002 to March 2004

Design, Site Development and Construction of the Caloocan City Hall Park with Commercial Area and Toll Parking Project
Scope of Works: Design, site development and construction of three – storey Toll Parking building.
Location: Philippines, NCR, Metro Manila, Caloocan City
Project Cost: PHP 217,499,000.00
Date Completed: December 2000 to November 2003

Pinatubo Hazard Urgent Mitigation Project
Scope of Works: Reconstruction of 9.6km Minalin Tail Dike, the construction of Gugu bridge, construction of evacuation road and channelization of Gugu creek.
Location: Philippines, Central Luzon, Pampanga
Project Cost: PHP 426,298,322.71
Date Completed: October 2000 to September 2003

Package 6B – Improvement of Secondary Roads Project (San Marcelino St./D. Romualdez St./Legarda St./Quezon Blvd.)
Scope of Works: This project consist of road repair works through removal and replacement of damaged PCC Pavement, the provision of a new asphalt concrete overlay, declogging of the existing drainage lines and the rehabilitation of the pedestrian sidewalks.
Location: Philippines, NCR, Metro Manila, Manila
Project Cost: PHP 49,652,418.78
Date Completed: June 2002 to August 2003

Construction of Tertiary Distribution System (Angat Water Optimization Project) at Tala Estate, North Caloocan
Scope of Works: Construction of tertiary distribution system at Tala Estate, Caloocan City.
Location: Philippines, NCR, Metro Manila, Caloocan City
Project Cost: PHP 138,533,616.00
Date Completed: July 2000 to April 2002

Construction of Port Harbor Causeway
Scope of Works: Construction of Causeway, break bulk / container yard / common berthing, pier (250 Lm) working apron, pier (300Lm)
Location:
Project Cost: PHP 124,279,308.96
Date Completed: December 1997 to October 2001

Design, Site Development and Construction of a Secondary Hospital & Medical Commercial Center
Scope of Works: Design, site development and construction of secondary hospital and medical commercial center.
Location: Philippines, NCR, Metro Manila, Caloocan City
Project Cost: PHP 202,999,777.00
Date Completed: December 2000 to June 2002

Rehabilitation / Reconstruction of Roads with Slips, Slope Collapse and Landslide – Secondary Roads, Tagudin – Cervantes Road (S00140LZ), Suyo, Ilocos Sur
Scope of Works: Construction of drainage and slope protection structures. Installation of active protection system along Tagudin – Cervantes
Location: Philippines, North Luzon, Ilocos Sur
Project Cost: PHP 57,338,819.85
Date Completed: Áugust 2020 to January 2021

Rehabilitation / Reconstruction of Roads with Slips, Slope Collapse and Landslide, – Tertiary Roads, Cervantes – Mankayan – Abatan Road
Scope of Works: Construction of drainage and slope protection structures. Installation of active protection system along Cervantes – Mankayan – Abatan Road
Location: Philippines, North Luzon, CAR, Mountain Province
Project Cost: PHP 57,338,819.85
Date Completed: Áugust 2020 to January 2021